The transmission capacity battle is a mess. NImby ...
https://www.pbs.org/newshour/nation...illion-energy-transmission-project-in-arizona
U.S. court rejects a request by tribes to block $10 billion energy transmission project in Arizona
https://www.pbs.org/newshour/nation...illion-energy-transmission-project-in-arizona
U.S. court rejects a request by tribes to block $10 billion energy transmission project in Arizona
Tohono O’odham Attorney General Howard Shanker argued during a hearing in March that claims by federal land managers that they could not find any evidence of the valley’s significance to area tribes was disingenuous at best. He referenced an academic book about the valley published by the University of Arizona Press and the declaration of a tribal member who once served as a cultural resource officer.
The transmission lines will forever transform “a place of beauty, prayer and solitude for generations of O’odham who want to connect with the spirits of their direct ancestors,” Shanker said. “So the irreparable harm is clear.”
Government representatives told the judge that the SunZia project is a key renewable energy initiative and that the tribes waited too long to bring their claims. They also argued that tribal representatives accompanied government officials in surveying the area in 2018 to identify and inventory any potential cultural resources.