You've done this sort of problem before --- Recognize this???produced by or involving two or more parties working together
that mean
A+B=?
A=30days
B=90days
Days required for both workers acting simultaneously to complete the job = 1/ ([the fraction of the work completed by 'A' per day] + [the fraction of the work completed by 'B' per day])