I am working on a feasibility study to distribute electricity from an energy centre to different sites through private wire. There is an existing HV ring main with numbers of Distribution Centres (DC) around it which operated by the client. I have attached a file showing the location of the energy centre, HV ring main with distribution centres and location of all sites that a proportion of their electrical demand would be supply from the Energy Centre through private wire. Could you please briefly explain for me how the private wire could be connected to the network to transmit electricity to each site i.e. does the private wire need to be connected to the nearest DC only or connections need to be made to all DCs or/and a new DC need to be implemented.
What problems and challenges could be faced in the network?
What problems and challenges could be faced in the network?